33
100 MeV IPF Project Summary
1.2.1 Facility Design 10.8
1.2.2 SFE Design 11.7
1.2.3 Project Management 12.6
1.2.4 Facility Construction 32.8
1.2.4 SFE Construction 27.9
1.2.5 System Testing 0.0 Contingency 4.2
WBS Description Percent
Project Completion:                 82%
BCP Approved                        10/29/01
UC Milestone #1 Achieved     12/19/01
UC Milestone #2 Achieved     01/11/02
C.P.I = 1.01;       S.P.I = 0.99
Baseline Schedule Complete: September 2003